Bulk Cement Requirement for Well Control
Most well control policy dictates there should be sufficient cement onboard to place a 500ft plug in the open hole
The formula used is: $$ X = \frac{\text{Length} \times \left(\frac{\text{Hole Size}^2}{1029.4} \right) \times 5.61458}{\text{yield}} $$
formula shown in Imperial form
Input all the necessary data and press calculate to get the answer